Construction Projects

2022 Projects

Chestnut Street Property Remediation - The city received a $3.3 million grant for cleanup/remediation of the 8.33-acre Chestnut Street Property, which has been a site for uncontrolled dumping. Site analysis work began in May 2022.
 

E Loveland Ave Gas Main 2022

East Loveland Avenue Gas Main Replacement — Duke Energy will replace a portion of gas main along East Loveland Avenue. Work is scheduled for Oct. 24-Dec. 2, 2022 (weather dependent). Daily work hours are 9 a.m. - 5 p.m. One lane of the road will be closed, and temporary traffic signals will be used. Some on-street parking along East Loveland Avenue will be restricted during the project. 


GPS Emergency Vehicle Traffic Signal Pre-emption Units - The 2022 budget includes $35,000 to continue progress on its plan to outfit traffic signals with GPS pre-emption technology to improve the response time of its fire and emergency vehicles and reduce intersection accidents. Units will be installed at the following intersections: Loveland-Madeira / Highridge, Loveland-Madeira / Valleyview, Rich / Fallis. Click here to read more about this technology.

Downtown Gas Project FINALHistoric Downtown Loveland Gas Main Replacement - Gas main replacement will occur Nov. 9-Dec. 30 (weather dependent) in several locations in Historic Downtown Loveland

  • the intersection of State Route 48/Second Street (near Graeter’s and the fire station)
  • along East Broadway Street from approximately the Five Points intersection to the trestle bridge
  • along Karl Brown Way from the trestle bridge to Harrison Avenue near Nisbet Park. 

Work will occur Monday-Friday after 9 a.m. Overnight work will not take place. Single lanes will be closed with two-way traffic maintained by flaggers. Some sidewalk access and on-street parking will be restricted as needed to facilitate the work.

Public Works Proposed BuildingPublic Works Facility - A new garage/office building is being constructed at the Public Works campus located along Loveland-Madeira Road. The facility is expected to be completed in Fall 2022. Click here for an overview article. Click here to watch a behind-the-scenes tour of the build.

Second Street/State Route 48 Improvement (Mobil Station) - The city, working in partnership with the Adams County Land Bank, took possession of the former Mobil Station site after the prior owner concluded fuel center and retail operations, thus clearing the way for the property to be transferred. With the cessation of fuel center activities on the site and the associated transfer of the property to the land bank, the city can now begin the process of completing the environmental inspections required to demolish the former fuel center, remove the existing underground storage tanks, pursuing additional funding to assist in remediating current known and unknown issues associated with the past fuel center use. To date on the site, asbestos testing work has been completed, which allows demolition efforts to proceed through the State of Ohio Demolition Grant program administered through Clermont County. Once testing results are confirmed, the county will then bid the demolition out as part of the grant process. Additionally, with the transfer of the property, the city authorized testing to determine if there are existing, undocumented petroleum releases associated with any active underground storage tanks on site. Once the site is remediated, a right turn lane will be added along SR 48 to improve traffic flow. 


Sr 48 Gas FINAL

State Route 48/Oakland Road Gas Main Replacement - Duke Energy will complete approximately 3-4 weeks of gas main work along State Route 48/Oakland Road from late November 2022 to January 2023. The road will be affected from the east end of St. Columban’s property (just past the football field) to the intersection of Loveland-Miamiville Road/Oak Street. This project will require day and night work. For day work, single lanes will be closed with two-way traffic maintained by flaggers. For night work, a portion of State Route 48 (at the Loveland-Miamiville intersection) will need to be fully closed for a portion of the project. The road will be fully closed from 9 p.m. – 6 a.m. with the road reopened during the day. Overnight traffic will be detoured.


2022 Completed Projects

Annual Road Program – The annual road program contract with JK Meurer Corp. was renewed on Jan. 12. The 2022 budget included $1,200,000 for the road program. The project began in late April 2022 with limited curb replacements. Roadway milling and paving began in June 2022. Paving took place through late October. 

Miamiview Culvert Replacement - The City of Loveland was awarded a $387,000 interest-free loan for a 20-year term from OPWC. The project included replacement of a concrete box culvert, headwalls, and wingwalls. The project also included extension of the dead-end roadway on (lower) Miamiview Drive to cross over the culvert and end with a T-type turn-around and paving. The project construction contract was awarded to JTM Smith Construction. Construction began in August 2021 and was completed in April 2022.

Matt Haverkamp Foundation Dog Park - The 2022 budget included $38,000 to install a dog park at the rear of Kiwanis Park. A grand opening ceremony for the park was held May 7, 2022. Learn the story behind the park name, and watch a video of the grand opening here.

Main & Chestnut Improvements - The City of Loveland received $1,132,900 of OPWC funding (50% as a grant, 50% as an interest-free loan) for this project. The scope of work included replacing the 4" cast iron water main, storm sewer improvements, and repaving on Main St., Chestnut St., S. Wall St., and Hill St. The project also included a complete replacement of the traffic signal at Wall St. and W. Loveland Ave., and upgrades to radar vehicular detection and GPS pre-emption there and at the traffic signal at Main St. and Loveland-Madeira Rd. Between October and the end of 2021, Ford Development Corporation completed water main installation, water service transfers, storm sewer improvements, and concrete repairs. From April through July 2022, traffic signal installation, paving, and sign installation work took place. 

Safety Center Lot paved 8-22Safety Center Parking Lot Expansion - JK Meurer Corp. was awarded the contract to expand the parking lots and create a new public entrance at the Safety Center.  Work was completed in August-September 2022.


Water Tower Cleaning -  The City of Loveland owns and maintains seven water storage tanks. The 2022 budget included $26,000 to clean the exteriors of three of the elevated water storage towers, those located at Union Cemetery Rd., Commerce Dr., and Lever Park. City Council awarded a contract to National Wash Authority dba Midwest Mobile Washers for the work. The tower at Commerce Dr. was cleaned on May 11. The Union-Cemetery Rd. tower was cleaned on May 12. The Lever Park tower was cleaned May 16.

2023 Projects

Bike Crossing RenderingAutomated Signal at West Loveland Avenue Bike Trail Crossing — The city has been awarded a grant to install an automated traffic signal system at the Little Miami Scenic Bike Trail crossing along West Loveland Avenue. To create the new system, two types of signals will be installed — traditional overhead traffic light signals for vehicles and traffic light signals designed for trail users. The system will deliver automatic traffic control and establish “Right of Way.” Currently, the West Loveland Avenue crossing has a pedestrian-activated flashing crosswalk system, and crossing guards work high-volume events to improve traffic flow through the crossing. Design work will take place in 2023 with the proposed installation in 2024. To review the 50% preliminary plans click here. These plans are for all phases and are subject to change. 



Nisbet GazeboNisbet Park Gazebo - The 2022 budget included $115,000 to install a gazebo in Nisbet Park, partially funded by an ODNR grant. Installation was planned for 2022 but is delayed due to supply chain issues. Construction is anticipated to begin in Spring 2023. In addition, a pathway will be installed to connect the gazebo to the Little Miami Scenic Trail.

Harrison Avenue Widening Project - The city is receiving $370,000 of State funding of an estimated $462,600 construction project to widen Harrison Ave. between Karl Brown Way and Railroad Ave. from 16'-20' existing width to 22' width. The project includes realignment and relocation of Harrison Ave. between Railroad Ave. and First St. to the north by approximately 70', in preparation for a planned 270-space parking facility.  Additionally, the project will include the installation of 5' wide concrete sidewalks and curb along the south side of Harrison Avenue.  These improvements will positively impact safety along the Little Miami Scenic Bike Trail, which has been a concern of the city's first responders. The project will also include the replacement of catch basins, upsizing of storm sewers, and addition of a headwall with flap valve at the pipe outlet, improving drainage and safety in the area.  Completion of the Harrison Avenue Widening Project will allow for the city to proceed with implementing the Nisbet Park Master Plan and corresponding improvements once the storm sewer outlet pipe through the park is complete.  Other improvements include enhanced signage, pavement markings, restoration, and other incidentals. 


Loveland-Miamiville Road Sidewalk Project — Sidewalks will be added along Loveland-Miamiville Road. Preliminary engineering occurred in 2022. Engineered construction drawings for Phase I of the project will begin in January 2023 and the project will be bid out. Construction may start as early as Spring 2023.

W Loveland Ave BridgeWest Loveland Avenue Bridge — The West Loveland Avenue Bridge is tentatively scheduled to be repaired in 2023. The bridge is owned and maintained by both Clermont and Hamilton County, and the project is being largely funded by Hamilton County, state grant funding and an allocation from the Clermont County Commissioners. The city is contributing funds toward decorative railing and new lighting. In 2021, the city and Hamilton County submitted a joint grant application to replace the north sidewalk, as well the railings, walls and bridge abutments. However, private utility relocation for conduit located within the sidewalks delayed the project. In July 2022, the north side of the bridge's sidewalk was paved with asphalt for pedestrian safety. The bridge will remain open to traffic with a reduced number of lanes during the repairs. As a project timeline is finalized, the city will publish construction dates.

OBannonville BridgeO’Bannonville Bridge  The Clermont County Engineer’s Office will replace the bridge on O’Bannonville Road near Hutchinson Road, which is located east of the city limits in Goshen Township. The county expects to begin construction in July 2023 and have it completed by fall. This project will require a roadway closure and detour route.

E Loveland Ave BridgeEast Loveland Avenue Improvements — In Fall 2023, immediately following road re-opening after replacement of the O’Bannonville Bridge, a joint project with collaboration from Clermont County, MSD, and the City will commence.  Clermont County is providing $478,320 for the replacement of the bridge on East Loveland Avenue over Bares Run, near #250 E. Loveland Ave. Metropolitan Sewer District (MSD) will replace and upsize about 1,300 LF of the sanitary sewer, from #220 to #362 E. Loveland Ave. MSD is paying a total of approximately $686,200 for the sanitary sewer work. The city is receiving $722,400 of State grant funding to install sidewalks on both sides of the road between #227 to #356, relocate water main around the bridge, make storm sewer system improvements, and repave the roadway while the bridge replacement project is being performed.  This project will require a roadway closure and detour route.


Nisbet Park Bridge (Little Miami Scenic Trail) — The Ohio Department of Natural Resources (ODNR) will replace the pedestrian bridge on the Little Miami Scenic Trail over O’Bannon Creek. This is the bridge just northeast of the restroom building in Nisbet Park. ODNR plans to replace the bridge during winter, when trail use is at its lowest.


Phillips_Park_Structure NDB 2

Phillips Park Playground - The 2022 budget included $60,000 to install a playground in Phillips Park to replace the one that required removal in 2021. While scheduled for 2022, the installation was delayed due to supply chain issues. The equipment is expected to be installed in Spring 2023.

Navaho and Cherokee Tot Lots - The city has received funding to replace the playgrounds in the tot lots, as well as add wifi service at both parks.  Project design is commencing, with a contract expected to be awarded in early 2023.

More Information

For more information about Loveland projects, please contact Cindy Klopfenstein, PE, CFM City Engineer, at 683-0150 or by email.